Synchronize Project Data with P6 EPPM

Synchronize project data when it is necessary to import or export data between Oracle Primavera Cloud and P6 EPPM.

To synchronize project data with P6 EPPM:

  1. In the object selector, select a project or workspace.
  2. In the sidebar, hover over Integration, and select Synchronize.
  3. Select Send P6 EPPM data to Primavera Cloud for Risks to view the objects and fields that will be synchronized when you run the business flow, and then select Close.
  4. In the Send P6 EPPM data to Primavera Cloud for Risks row, select Context, and then select Run.

    Note: In order to synchronize risk data, the selected project must be stored in a workspace assigned to a P6 EPPM connection that contains the Send P6 EPPM data to Primavera Cloud for Risks business flow.