Reset the Project CBS

You can reset the project CBS if your project cost code needs change if the following conditions are met:

To reset the project CBS:

  1. In the object selector, select a project.
  2. In the sidebar, hover over Cost and Funds, and select Cost Sheet.
  3. On the Cost Sheet page, select the Actions menu, and then select Reset CBS.