Close Out a Reporting Period

Closing out reporting periods enables project managers and other stakeholders to analyze the progress of projects using reports, identify problem areas, and take corrective actions as necessary over the life of the project. Ensure progress is updated before you close out a reporting period. When a reporting period is closed, installed and actual to date values are locked down for the selected date and can no longer be updated.

You must have the appropriate security privileges to close out reporting periods.

Before the first reporting period is closed, the following conditions must be met:

To close out a reporting period:

  1. In the object selector, select a project.
  2. In the sidebar, hover over Scope, and select Period Closeout.
  3. On the Reporting Period Closeout page, select Close Period.