Appropriate a Fund
After a fund has been added or allocated to a project, a portion of that fund can be appropriated, meaning it is committed to work on the project.
To appropriate a portion of a fund:
- In the object selector, select a project.
- In the sidebar, hover over Cost and Funds, and select Project Funds.
- In the Status view, select a fund row.
- In the Appropriated field, enter the portion of the fund that you want to commit to work on the project.
- Select Save.
Tips
- To add and remove columns on this view, select Settings.
- You can appropriate a time-phased fund for each period of its lifecycle on the Time Phase view.