Prioritize Projects for Execution on the Resource Planning Page

During the resource planning process, allocating work units to project roles may not be able to resolve all availability constraints. Excluding lower priority projects from the scenario may help to create additional role availability for the higher priority projects in your portfolio.

Use the Resource Planning page to include and exclude projects from your scenario. View the effects on role availability in the table and in the charts and histograms in the Role Availability detail window. In the Stacked Histogram, colored segments in each bar represent the total allocation of a specific project. Bars that exceed the Max Capacity line in the histogram have exceeded the total role capacity for that time period. Exclude one or more projects or adjust role allocations to satisfy the capacity limit.

To prioritize projects for execution:

  1. In the object selector, select a portfolio.
  2. In the sidebar, hover over Resources, and select Resource Planning.
  3. Select an in-progress scenario.
  4. To include a project in a resource plan scenario, in the table, select the State field to display Selected or Forced In. To add multiple projects at once, use Ctrl + click to highlight each project. Select the Actions menu, select Include, and then select Highlighted Projects.

    Note: If a project must be included in the resource plan, select Forced In. Conversely, if it has been determined that a project will not be included in the resource plan, select Forced Out.

  5. In the Role Availability detail window, select Stacked Histogram to view the effects of including or excluding a project. To change the field displayed in the histogram, select Settings, and then select a field on the Chart Settings tab.
  6. Select Save.

Tips