Add a Microsoft Project Connection

Set up a Microsoft Project integration to use existing data from Microsoft Project to create projects in Oracle Primavera Cloud.

To add a Microsoft Project connection:

  1. In the object selector, select Global Admin.
  2. In the sidebar, select Integrations.
  3. In the Microsoft Project tile, select Integrate.
  4. Select the Connect tab.
  5. Complete either of the following steps:
    • Select Enable Import/Export for all Workspaces to enable or disable the Microsoft Project connection for every workspace in the application.
    • In the Workspaces field, select one or more Primavera Cloud workspaces to which this connection applies. Data from this Microsoft Project connection will only be available for the selected workspaces.

      Note: You can only select workspaces in the Workspaces field if the Enable Import for all Workspaces switch is disabled.

  6. Select Save.