Recalculate Costs on the Summary Cost Sheet for a Program

The information on the Summary Cost Sheet can come from many projects. Use Recalculate to make sure the Summary Cost Sheet shows the most up-to-date cost information.

To recalculate costs on the Summary Cost Sheet:

  1. In the object selector, select a program.
  2. In the sidebar, hover over Cost and Funds and select Summary Cost Sheet.
  3. On the Summary Cost Sheet page, select Recalculate.