Link Timesheet Actual Hours and Assignment Actual Units
Linking timesheet actual hours to assignment actual units copies the timesheet actual hours to resource assignment actual units and timesheet actual start to the resource assignment actual start.
To link timesheet actual hours to assignment actual units:
- Navigate to the project settings page
- In the object selector, select a project.
- In the sidebar, select Summary & Settings.
- On the Summary & Settings menu, select Settings.
- In the Timesheet Actual Hours section, select the Link Timesheet Actual Hours and Assignment Actual Units option to link approved timesheet hours and assignment actual units and dates.
Note: Additionally, the timesheet actual hours are copied to the Timesheet Actual Units row on the Assignment List page.
- Save your changes:
- Select Save.
- In the Summary & Settings panel, select Close.
Last Published Tuesday, May 21, 2024