Configure the Schedule Variance Analysis Panel

Configure comparison options to determine what is displayed on the Schedule Variance Analysis panel.

To configure the Schedule Variance Analysis panel tab options:

  1. Navigate to the Schedule Comparison page
  2. In the Settings panel, select the Comparison Panel tab.
  3. To configure the comparison panel, select from the following:
    1. In the New section, select the new items to display:
      • New Activities
      • New Relationships
      • New Resources Assignments
      • New Risk Mappings
    2. In the Deleted section, select the deleted items to display:
      • Deleted Activities
      • Deleted Relationships
      • Deleted Resource Assignments
      • Deleted Risk Mappings
    3. In the Changed section, select the changed items to display:
      • Changed Scheduler Settings
      • Changed Project Values
      • Changed Entered Values
      • Changed Calculated Values
      • Changed Relationships
      • Changed Resources Assignments
  4. Select Apply.