Add a Work Package Change Request

Add work package change requests when it is determined that new work packages need to be added to the project, new scope assignments need to be added to work packages, the scope assignment quantity or hours needs to be adjusted, or when scope assignments need to be transferred. One change request can capture as many change items as needed.

To add a work package change request:

  1. In the object selector, select a project.
  2. In the sidebar, hover over Scope, and select Work Package Changes.
  3. Select Add Work Package Change.
  4. On the Work Package Change Details page, in the Description field, optionally enter the purpose for the change request and select Save.