Copy a Project CBS

Copy the CBS of a sibling project if your project will use the same CBS.

To copy a sibling project CBS:

  1. In the object selector, select a project.
  2. In the sidebar, hover over Cost and Funds, and select Cost Sheet.
  3. On the Cost Sheet page, select Create CBS.
  4. In the CBS Setup dialog box, select Copy from other, and select Next .
  5. Select a CBS to use, and select Next .
  6. Select the CBS codes you want to include, and select Next .
  7. Select one or more budget or actuals sources, and select Finish.