Perform Scope Management When Connected with P6 EPPM using Primavera Gateway

If your project is being worked on simultaneously in P6 EPPM, coordinate with the scheduler to import and export data between Oracle Primavera Cloud and P6 EPPM.

For performing tasks in P6 EPPM, refer to P6 EPPM Help.

To perform scope management, the following sequence is recommended.

  1. In Oracle Primavera Cloud:
    1. Create the project.
    2. Set the EPS Code. This code determines where the project will reside in the EPS in P6 EPPM.
    3. Create the PBS.
    4. Add the scope items.
    5. Create the WBS.
    6. Create the work packages.
    7. Send the project to P6 EPPM.
  2. In P6 EPPM:
    1. Open the project. You will see the WBS structure and work packages as defined in Oracle Primavera Cloud.
    2. Add activities to work packages.
    3. Send the project to Oracle Primavera Cloud.
  3. In Oracle Primavera Cloud:
    1. Select the Activity Weight Method for the work packages. This value lets you decide which aspect of the activity is used to derive the Activity Percent Complete.
    2. Review the activities assigned to work packages using the Activities detail window.
    3. If the Activity Weight Method is Manual, enter weights for each activity. These weights are used to calculate the Activity Percent Complete.