Scope Assignments: Time Phase Fields

Depending on your settings, the following fields might appear on the page as table columns, spreadsheet rows, or in detail windows. Fields that are generic across the application, such as Name, may not be included here.

Financial

Actual Cost to Date

The actual costs incurred on the scope assignment. This tracks the VOWD (Value of Work Done).

Approved Change Cost

The sum of all approved cost changes in the change records for the scope assignment.

Baseline Cost

The Revised Cost at the time the current baseline was set.

Incremental Installed Cost

The total cost incurred on the scope assignment as of the current date.

If Rate By is set to Hours, then Installed Cost equals Revised Cost Rate multiplied by Installed Hours.

If Rate By is set to Quantity, then Installed Cost equals Revised Cost Rate multiplied by Installed Quantity.

Original Cost

The original cost of the scope assignment.

If Rate By is set to Hours, then Original Cost equals Original Hours multiplied by Original Cost Rate. If this value is entered manually, then Original Cost Rate is recalculated to equal Original Cost divided by Original Hours.

If Rate By is set to Quantity, then Original Cost equals Original Quantity multiplied by Original Cost Rate. If this value is entered manually, then Original Cost Rate is recalculated to equal Original Cost divided by Original Quantity.

Manual updates can only be performed on the Plan view, not on the Time Phase view.

Pending Change Cost

Calculated as the sum of all pending cost changes in the change records for the scope assignment.

Remaining Early Cost

The amount left to be spent.

If Rate By set to Hours, then Remaining Cost equals Remaining Hours multiplied by Revised Cost Rate.

If Rate By set to Quantity, then Remaining Cost equals Remaining Quantity multiplied by Revised Cost Rate.

Remaining Early and Remaining Late fields display for time phased scope assignments to account for the Remaining Early and Remaining Late date fields.

Remaining Late Cost

The amount left to be spent.

If Rate By set to Hours, then Remaining Cost equals Remaining Hours multiplied by Revised Cost Rate.

If Rate By set to Quantity, then Remaining Cost equals Remaining Quantity multiplied by Revised Cost Rate.

Remaining Early and Remaining Late fields display for time phased scope assignments to account for the Remaining Early and Remaining Late date fields.

Revised Cost

The Original Cost before the baseline is set. After the baseline is set, Revised Cost equals Original Cost plus Approved Change Cost.

Hours

Actual Hours to Date

The number of hours spent on this scope assignment since the last progress date. This value is added to Cumulative Actual Hours to Date.

Approved Change Hours

The sum of all approved change hours in the change and transfer records for the scope assignment.

Baseline Hours

The Revised Hours at the time the baseline was set.

Incremental Installed Hours

Hours spent on the scope assignment.

Calculated as Installed Quantity multiplied by Revised Productivity Rate.

Original Hours

The original expected hours needed to complete all the work required to install the material quantity on the scope assignment.

Calculated as Original Quantity multiplied by Original Productivity Rate.

Before the baseline is set, this field can be entered manually. A manual entry recalculates the Original Productivity Rate to equal Original Hours divided by Original Quantity.

Pending Change Hours

Calculated as the sum of all pending hour changes in the change records for the scope assignment.

Remaining Early Hours

The number of hours left for the scope assignment.

Calculated as Remaining Quantity multiplied by Original Productivity Rate.

Remaining Early and Remaining Late fields display for time phased scope assignments to account for the Remaining Early and Remaining Late date fields.

Remaining Late Hours

The number of hours left for the scope assignment.

Calculated as Remaining Quantity multiplied by Original Productivity Rate.

Remaining Early and Remaining Late fields display for time phased scope assignments to account for the Remaining Early and Remaining Late date fields.

Revised Hours

Original Hours before the baseline set. After the baseline, Revised Hours is equal to Original Hours plus Approved Change Hours.

Units

Actual Quantity to Date

That amount of material or product that has been installed since the last progress date.

Approved Change Quantity

Calculated as the sum of all approved change quantities in the change records for the scope assignment.

Baseline Quantity

The Revised Quantity at the time the current baseline was set.

Installed Quantity

That amount of material or product that has been installed since the last progress date.

Original Quantity

The expected amount of material or product required.

Pending Change Quantity

The sum of all pending change quantities in the change records for the scope assignment.

Remaining Early Quantity

The quantity remaining for the scope assignment.

Calculated as Revised Quantity minus Installed Quantity.

Remaining Early and Remaining Late fields display for time phased scope assignments to account for the Remaining Early and Remaining Late date fields.

Remaining Late Quantity

The quantity remaining for the scope assignment.

Calculated as Revised Quantity minus Installed Quantity.

Remaining Early and Remaining Late fields display for time phased scope assignments to account for the Remaining Early and Remaining Late date fields.

Revised Quantity

The total quantity that has been revised to account for approved changes for a scope assignment. This value equals the Original Quantity before the original baseline is set.

Calculated as Original Quantity plus Approved Change Quantity. Revised Quantity equals the Original Quantity before the original is baseline set.