Update the Data Date When Progressing a Work Package and Scope Assignment

When adjusting work package or scope assignment dates, update the data date to adjust all key date fields. This will adjust the Original, Planned, Revised, and Remaining dates.

Note: This only applies when activities are not linked to work packages or scope assignments.

To update the data date:

  1. In the object selector, select a project.
  2. In the sidebar, hover over Scope, and select Work Packages.
  3. Select Modify Dates.
  4. In the Modify Dates dialog box, select a new data date and select Modify.

Tips