View Risk Removal Impact Analysis Results

View which risks could have the greatest impact on the project cost and finish date. Set viewing and filtering options to narrow the results that are included in the tornado chart.

Note: You must enable the risk removal impact analysis in the analysis settings to view these results.

To view risk removal impact analysis results:

  1. In the object selector, select a project.
  2. In the sidebar, hover over Risk, and select Risk Analysis.
  3. Select the Risk Removal Impact tab.
  4. In the Response Context list, select an analysis context:
    • Pre-Response: Displays analysis results based on pre-response values.
    • Post-Response: Displays analysis results based on post-response values.
  5. To view risk removal impact results for the project cost, select the Cost tab. To view impact results for the project finish date, select the Finish Date tab.
  6. Select Settings to configure the following filtering options:
    1. Ignore values smaller than +/-: Enter a minimum percentage value for which to include results. Results that fall below this value will be omitted from the tornado chart.
    2. Show top: Select the number of risks to display, beginning with the highest impact value.
    3. Select Save.

Tips