Logging Hardcopy Submittals Received from a Subcontractor and Sent as a Hardcopy to a General Contractor or Construction Manager
When logged into Submittal Exchange, select a project and go to the appropriate log.
- Select the description for the section to which you are uploading a hardcopy. A dialog box appears.
Note: If the item you are submitting is not in the Descriptions column for the section, select the green upload arrow and add a description to the Other option.
- Complete the Date received from subcontractor field.
- Select Hardcopy under Received from subcontractor. Two drop-down fields appear next to the Hardcopy field.
Select the number of hard copies in the first field and choose between Samples or Hardcopy from the second.
- Under the Submittal to Architect area select Hardcopy.
- Enter the date under Date Sent.
- In the Priority drop-down box select an appropriate priority.
- If applicable, add comments in the Remarks from GC field.
- Select Save.
Note: An email notification is sent to the Architect/Final Reviewer letting them know a hardcopy is in transit to them.