How a Project Leader Can Edit Punchlist Status Options

When logged into Submittal Exchange, select a project and go to the Preferences tab.

  1. Select the log that you would like to edit.
  2. Select the Edit Status Options button below the Log Type.
    • The current Status Options will be displayed.

      Note: Any item with a red asterisk is a required item, however you may still edit the text that is displayed.

  3. Edit, remove, or add new Status options.
  4. If you would like to add additional options, click the +Add Additional Status Options link and type in the text you wish to appear.
    • Select Done, at the bottom of the list when complete.
  5. Select Save at the bottom of the window.

    Note: Subcontractors will only be able to select the second status option that is available to subcontractors upon their completion.