Backing Out an Architects Review
Project Leaders can use Edit Detail to back out of a review.
When logged into Submittal Exchange, select a project and go to the Submittal Log.
Note: When using Edit Detail, most automation is disrupted and the appropriate email notifications may not go to the team members.
Backing out a Final Review
- Select the description of the submittal that needs to be backed out. A dialog box appears.
- Select Edit detail in the upper right corner.
- Select Architect Review.
- Remove the following by highlighting the text and using the delete key on your keyboard:
- Date returned to General Contractor
- Action code
- Remarks, if entered.
- Change the file type to Hardcopy.
- Select Return to Subcontractor. Remove the Return to Subcontractor date displayed in this area.
- Select Save.
Backing Out a Consultant Review
- Select the description of the submittal that needs to be backed out. A dialog box appears.
- Select Edit detail in the upper right corner.
- Select Consultant Review.
- Remove the following by highlighting the text and using the delete key on your keyboard:
- Date reviewed
- Action code
- Remarks, if entered.
- Change the file type to Hardcopy.
- Select Architect Review.
- Remove the following by highlighting the text and using the delete key on your keyboard:
- Date returned to General Contractor
- Action code
- Remarks, if entered.
- Change the file type to Hardcopy.
- Select Return to Subcontractor. Remove the Return to Subcontractor date displayed in this area.
- Select Save.
Backing Out a GC Review
- Select the description of the submittal that needs to be backed out. A dialog box appears.
- Select Edit detail in the upper right corner.
- Select Submittal from GC.
- Remove the following by highlighting the text and using the delete key on your keyboard:
- Date received from GC
- Date Sent to Architect
- Remarks, if entered.
- Change the file type to Hardcopy.
- Select Consultant Review.
- Remove the following by highlighting the text and using the delete key on your keyboard:
- Date Sent to
- Date Reviewed
- Action code
- Remarks, if entered.
- Change the file type to Hardcopy.
- Select Architect Review.
- Remove the following by highlighting the text and using the delete key on your keyboard:
- Date returned to General Contractor
- Action code
- Remarks, if entered.
- Change the file type to Hardcopy.
- Select Return to Subcontractor. Remove the Return to Subcontractor date displayed in this area.
- Select Save.