Changing an Expected Item from a Submittal to a Closeout or from a Closeout to a Submittal

When logged into Submittal Exchange, select a project and go to the Sections & Categories tab.

  1. Select the section that needs a submittal or closeout item adjusted. The section number and name highlight in blue.
  2. From under the Expected items in this section: box, select Edit.
  3. Select either Submittal or Closeout from the drop-down list for the expected item.
  4. Select Save.