Data Mapping During EnterpriseTrack Export

General

ET Field

MS Project Field

Currency Symbol

Symbol

Positive Currency Format

Placement X

 

Number of Decimal Places

Decimal digits

Scheduling Mode

ET Activity Schedule Mode

MS Project Task Type

Duration and % resource availability

Fixed Duration - non effort driven

Effort at activity level - Equal distribution

Fixed Work

Effort at activity level - Unequal distribution

Fixed Work

Effort at resource level (Summary)

Fixed Work

Effort at resource level (Detailed)

Fixed Work

Note: Scheduling Mode in EnterpriseTrack maps to Task Type in MS Project.

Calendar

ET Field

MS Project Field

Work Hours Per Day

Hours per day

Work Hours Per Week

 

Hours per week

Start Fiscal Year

Fiscal year starts in

Project

ET Field

MS Project Field

Project Name

Title

Comments

Comments

Default Project Calendar

Calendar

Cost

ET Field

MS Project Field

Team Member rate

Rate based (standard or overtime)

Equipment rate

Material (rate based)
Cost Resource (cost)

Cost-planned_fixed

Fixed Cost

cost- planned_material

N/A

cost - actual_material

N/A

Resource

ET Field

MS Project Field

Et_tm_id

Text30

ET_user_id

Text29

ET_role_id

Text28

ET_role_name

Text27

ET_1nameET_fname

Name

Resource type (person or equipment)

Type (work= person or equipment)

Resource calendar

Resource Calendar

Activity Dates

ET Field

MS Project Field

Baseline_start_date

Baseline Start

Baseline_completion_date

Baseline Completion

Baseline_duration

Baseline Duration

Planned_completion_date

N/A

Planned_duration

Duration

Actual_start_date

Start
Actual Start

Actual_completion_date

N/A

Actual_duration

Actual Duration

Planned_duration

N/A

Actual_duration

N/A

Activity

ET Field

MS Project Field

Name

Name

Comments

Notes

Activity_id

Text30

% completion

% completion

Owners

Owner

Activity marked NA

Text29 is set to NA_Closed

WBS Code

WBS

Milestone

Milestone

Critical tasks

Tasks are critical if slack is less than or equal to 0 days.

Notes:

See Also

Data Mapping for EnterpriseTrack and MS Project

Data Mapping During EnterpriseTrack Import



Legal Notices
Copyright © 2000, 2018, Oracle and/or its affiliates. All rights reserved.

Last Published Thursday, May 03, 2018