Complete an Activity or Milestone
When you have completed all of the work required by an activity or milestone, mark them complete.
To mark a milestone or activity complete:
- Navigate to the Project Home screen.
- Tap the
My Activities tile.
- On the Activities screen, select an activity.
- On the Details screen, tap Edit.
- On the Edit Activity screen, tap Complete Activity or Complete Milestone.
Which one you see depends on whether you've been assigned the activity as an activity owner or resource assignment.
- Tap Done.
Tip
- There is another way to mark activities and milestone complete. In the activity list, drag the activity to the left until the
Complete icon appears. Then, tap Complete.
Last Published Tuesday, September 2, 2025