Start an Activity
You must mark your activities as started before you can update their progress.
To mark an activity as started:
- Navigate to the Project Home screen.
- Tap the
My Activities tile.
- On the Activities screen, select an activity.
- On the Activity Detail screen, tap Edit.
- On the Edit Activity screen, tap Start Activity or Start Assignment.
Which one you see depends on whether you've been assigned the activity as an activity owner or resource assignment.
- Tap Done.