Backup PMAC background task

The Backup PM&C command lets the PMAC application begin executing a background task to back up the PMAC server data to the specified location.

If an authorized user deletes an in-progress Backup PM&C background task, the deletion stops the tracking of its status, but not its execution.

Only one Backup PM&C background task can run at a time. An error is issued if an attempt is made to start a new Backup PM&C background task before the first background task completes.

On the Background Task Monitoring page on the PMAC GUI, you can monitor the progress of the Backup PM&C background task. The Status field shows the current step being executed.