Add Enclosure background task steps

The table shows the steps associated with the Add Enclosure background task. Note that as a step completes, the page must be refreshed for the next step to display.

Table 6-1 Add Enclosure Steps

Step Status Field Description
1 Starting Add Enclosure. The user has initiated the Add Enclosure command via the PMAC GUI and the PMAC application begins the Add Enclosure background task.
2 Configuring Enclosure. Starting the OpenHPI daemon to monitor the enclosure.
3 OpenHpi Daemon Started. OpenHPI Daemon has been spawned.
4 Enclosure added - starting monitoring. The smacMon process has established communication with the enclosure and monitoring has begun. The Add Enclosure background task is complete.
5 Success.