In the Asset Dispatch Board, you can schedule activities by selecting an activity record from the Unscheduled Activities list and then moving the record to the Gantt chart.

This task is a step in Process of Managing Assets.

To schedule an activity for an asset

  1. Navigate to the Assets screen, then the Dispatch Board view.
  2. In the Date field, enter the date that you want to schedule activities.
  3. Make sure that the asset for which you want to schedule activities appears on the Gantt chart.
  4. In the Unscheduled Activities list, select an activity record and (without releasing the selection) then move the activity to the Gantt chart and place the activity on the appropriate asset and time interval.