Known Issues

Payment Authorization

The Payment Authorizations page (made available in 25.12) is not listing invoices for organizations with a role of General Contractor in the system. This can occur when a General Contractor is self performing work on a project and submitting an invoice to the General Contractor managing the project.

You may be impacted if:

Next Steps: If you think you may have been impacted by this system issue:

You can access payments pending authorization from the project context. Use the legacy page to validate all payments for a draw match the enterprise Payment Authorizations page to avoid missing any payment authorizations for a given project and or period.

Reports - (Resolved)

Reports created using the Selected Segments filter may generate a file with no data.

Next Steps: If you think you are impacted by this system issue:

Potential Lien Waiver Tracking Issue - (Resolved)

The Textura team recently identified and addressed a system issue. As a result, it is possible that some Manual Contractors and Lien Waiver Only Sub-Tiers may not have been properly included in a draw even if a Lien Waiver amount was recorded for them if they were previously marked as being final.

You may have been impacted if:

Next steps: If you think you may have been impacted by this system issue:

Review your sub-tier waivers to identify if any had lien waiver amounts recorded in a draw where the sub-tier was not also included in the draw.

Instruction to Manually add Sub-Tiers

General Contractors can use the following steps to manually include impacted Sub-Tiers:

  1. Log into your Textura Payment Manager account.
  2. Navigate to the Project Home page for the project which includes the Sub-tier you wish to add.
  3. From the Compliance menu select Manage Lien Waivers by Draw.
  4. From the Contract drop-down list, select the Sub-tier you wish to edit.
  5. Select the Included in Draw checkbox for the appropriate draw.
  6. Click Save.