Include New Subcontractors in Reopened Draws
General Contractor
When a draw is reopened, subcontractors may have been added to the project who were not present when it was closed. These subcontractors are now available to select as participants in the reopened draw.
Release 24.4
The Invoice Control Log Now Retains Details of Invoices Removed from a Draw
General Contractor Owner
Use the Invoice Control Log to view the history of invoices removed from a draw. This includes invoices removed due to draw closure, or because the draw was declined by the subcontractor.
Improved Invoice Rejection Messaging
Owner General Contractor
Warnings are now displayed when rejecting an invoice, detailing the draws that will be rejected and require resubmission, and other consequences of rejecting the invoice.
Release 24.3
Automatically Include Sub-tiers in Draws
General Contractor Owner
Use the new project setting to automatically include lien waiver only and manual sub-tiers in a draw when their parent organizations are invited. This setting is enabled by default, and can be disabled on a project-by-project basis.