Edit WB Tab of Subcontractor Work Breakdown
Use the Edit WB tab to view the budget and adjust un-billed line items.
Adjustment Amount
Used to change line item amounts.
Work Breakdown Amount
Current value for the line item, including Adjustment Amount.
Net Change by Variation Amount
Total value of variations (positive or negative) that impact the line item.
Contract Sum to Date Amount
Value of the line item plus the Net Change by Variation amount.
Billed to Date Amount
Amount claimed to date (this value changes based on Period Context).
% Comp
Percentage of the line item completed so far.
Balance to Complete
Amount left to bill on the contract (the total amount of work outstanding on the contract). This amount equals the Contract Sum to Date Amount minus the Billed to Date amount.