View Period Fields Overview
The following columns are displayed on both pages:
Description
Describes the line item.
Scheduled Values
Current value for the line item. This includes the Adjustment Amount.
Work Completed
From Previous Application: Dollar amount of the work completed through the last claims period.
This Period: Dollar amount of the work completed between the Period From and Period To dates.
Material Stored This Period
Dollar amount of material stored between the Period From and Period To dates.
Total Completed and Stored to Date
Dollar amount of the material completed and stored from the start of the project (Work Completed From Previous Application + Work Completed This Period + Material Stored This Period).
% Complete
The percentage of work completed in the current and all previous periods.
Balance Due
The amount left to finish against the line item.
Tip
Use this page to quickly verify amounts billed for each subcontract, the percentage of work completed, retention held, and whether or not variations are included in that period data.
View Period Request – WB
See a line-by-line breakdown of approved Subcontractor claims and self-performed amounts on the View Period Request – WB tab. It includes an additional column. The WB is short for Work Breakdown.
Item
The number used to sort line items sequentially
View Period Request – SC
See a summary of all approved subcontractor claim amounts, including the selected period (as identified at the top of the page) on the View Period Request – SC tab. The SC is short for Subcontract.
Tip
Use this page to quickly verify amounts billed for each Subcontract, the percentage of work completed, and retention held.
The table is organised by Subcontract. It includes additional columns.
Sub Contract
Links to the View Period Request – WB page for the subcontract.
Sub Contractor Description
Identifies the Subcontractor
Links to the claim documents
Document links appear based on the Document Settings selected by the Head Contractor on the Project Settings page.
Progress Claim, Statement, Statutory Declaration and Payment Schedule links open a dialogue box to download PDF versions of the selected document.
The Attachments link opens the Attachments page.
The Progress Claim Log link opens the Progress Claim Log page.