Recording Progress for Head Contractors

Before you Begin

Approve Subcontractor progress claims before creating the client claim. Ensure all required Subcontractor claims have been received and approved. If you send your progress claim to the Signer before approving a Subcontractor's claim, the Subcontractor will be excluded from the period.

Recording you Progress

  1. Navigate to your Billing Workflow
  2. Choose a line to bill against. Your total lines may be pre-filled with your Subcontractor invoice amounts based on your project settings. You can select a cell to overwrite the amount.
    1. Enter a dollar amount in the Work  This Period column for each line item.
    2. Optional. To bill based on percentage, update the % Complete columnThe Work This Period  field shows the dollar amount. Note: If you are using Unit Price Billing, see Billing by Units to enter a progress claim using unit amounts instead of dollar amounts.
    3. Optional. Enter the dollar amount of material stored between the draw Period From and Period To dates in the Material Stored This Period field.
    4. Review the value in the Net This Period.
  3. (Optional) Add comments to a line for later review or as a message to an on-system user.
    1. From the Description of Work column, select the Comment icon for a line item.
      A Comments and History dialog box displays.
    2. In the Comment text box, enter text.
    3. Select OK.
      The dialog box closes and the Comment icon is shaded blue to indicate that a comment is associated with the invoice line.
  4. (Optional) Set invoice codes.
    1. From the Table View, select Standard + Codes.
    2. For each line item select the appropriate codes.
  5. Select Save & Continue to move to the next tab in your Billing Workflow.

Tips: