Configuring Owner Funding Settings
As a Main Contractor, use the Track Owner Funding feature to track the date an Owner funds a period on the system.
- Set up the Project.
- Navigate to the Project Settings Page
- Once the Create Project Participants page is completed, the system displays the Project Settings page.
- After creating a project, choose Project Settings under the Project Setup menu at the top of any page.
- From the Project Settings page, select the Track Owner Funding setting under the Project Information section.
The Owner Funding section will display on the Period Home page.
- Navigate to the Project Settings Page
- (Optional) Select the Payment Due Date setting to generate the date payments should be disbursed to Subcontractors after the Owner funds a draw.
Tip
Include an Owner Funding Manager
The Track Owner Funding Date setting requires a project include an Owner Funding Manager. The Owner Funding Manager role can only be assigned to users with Manage Owner Funding permissions.