Locking Current Period Retention on a New Subcontract
To lock retention on a new subcontract:
- Create the Main Contractor Work Breakdown (WB).
- To prevent the subcontract from auto-completing, create at least two line items in the Main Contractor WB.
- Create a new subcontract.
- From the Contract Maintenance page, select the Subcontractor cannot modify retention setting.
- Select the Create Contract button.
A status page confirms the contract has been created. The Subcontractor must accept or decline the subcontract to participate on the project.