Deleting an Accepted Subcontract

There are certain instances in which you may need to delete a subcontract linked to your project. Since Textura holds legal documents and facilitates Subcontractor payment applications, Project Managers can only delete a confirmed subcontract after meeting the following criteria:

As long as the subcontract fits the above criteria, a user with a Project Manager role can delete the subcontract from the Contract Maintenance page.

Accidentally assign a subcontract to an incorrect Subcontractor organisation and the Subcontractor has not yet accepted project participation? You can reassign the subcontract instead.

To delete an accepted subcontract:

  1. Navigate to the Variations Page
  2. From the Variations page, select the +Add button.
  3. Create a negative variation to bring the subcontract value to zero.

    See the Creating a Subcontract Variation for Main Contractors topic for a step-by-step guide on creating a subcontract variations (SV).

  4. Navigate to the Contract Maintenance Page
  5. If your subcontract meets the criteria listed above, a Delete Subcontract button displays. Select the Delete Subcontract button.

    A Delete Subcontract dialogue box displays.

  6. In the dialogue box, select a reason for deleting a subcontract from the drop-down list. This is a mandatory step and you cannot delete a subcontract without selecting an option.
  7. Select the Delete button.

    After you delete the project, the following will happen:

    • If the you or the Subcontractor already paid the usage fees for the subcontract, a refund of these fees will occur in 5-7 business days
    • The Subcontractor receives an email about the deleted contract.