Working With the My Document Status Page

  1. Project: The name of your project. Use the Project drop-down menu to select a different project or contract. It defaults to the selected project if you navigate to the My Document Status page from the Legal Document Update page.
  2. Due on Site: The date when the documents are due.
  3. Status: The status of a document requirement. Use this column to determine which documents must be submitted or updated. The legend defines each status.
    Look at the Status column to see the status of a document requirement.
    • Green means a requirement is compliant.

      A document is displayed as Received once the Compliance Manager updates the document status.

    • Yellow means:
      • A Standard requirement expires within 60 days.
      • A Periodic requirement has not been received in a period without an approved invoice.
    • Red means:
      • A Standard requirement expired or was not received.
      • A Periodic requirement has not been received in a period with an approved payment application.
      • A Conditional requirement has not been received in a period when a subcontract meets a preset condition.
    • Grey means
      • A Standard requirement is not tracked.
      • A Periodic requirement is not tracked and no more documents are expected.
      • A Periodic requirement is not applicable for the scheduled period.
      • A Conditional requirement is not applicable.
  4. Submit and View: Use the Submit link to submit documents and the View link to view uploaded documents. For more information, see Submitting Documents and Viewing Uploaded Documents.
  5. When Expired or Missing: Describes the enforcement and consequences for missing documents.
    • Withhold Payments
      • A notification is sent by the system when the document is out of compliance.
      • Payments are held until the document is in compliance with the requirement.
    • Advise Only: A notification is sent by the system when the document is out of compliance.
  6. Subcontractor Instructions: Shows specific directions added by the Main Contractor.