Sign Sub-Tier Document
As a Lien Waiver Only Sub-Tier (LW Sub) or Supplier, you will use the Sign Sub-Tier Document page to sign lien waivers. The General Contractor selects the type of lien waiver that must be signed as part of the project setup.
Notes:
- A General Contractor or a Prime Subcontractor must request for you to sign a lien waiver in order for the page to display.
- Depending upon project settings chosen by the General Contractor, you may need to enter Contractors and Material Suppliers on the Record Sub-Tiers tab before the system prompts you to sign a lien waiver.
- The Payment Amount entered by your Prime Subcontractor displays at the top of the page.
- Once you sign a lien waiver, a signed copy of the document will be available to the General Contractor and your Prime Subcontractor.
Last Published Wednesday, July 10, 2024