Adding a Lien Waiver Only Sub-Tier for General Contractors
To add a Lien Waiver Only Sub-Tier (LW Sub) from the Add Sub-Tier page:
- Navigate to the Add Sub-Tier Page
Navigate to the Add Sub-Tier page from the Manage Lien Waivers or View Lien Waiver Status page:
- To add a Manual Contractor or Supplier under the General Contractor, choose the plus symbol (+) in the Organization column heading.
- To add a Manual Sub-Tier Subcontractor or Supplier, choose the Add Sub-Tier link from the drop-down next to the Prime Subcontractor under which the Supplier should appear.
Note: An on-system Subcontractor must be included in the draw for its name to display on the Manage Lien Waivers page.
- In the name, begin typing the name of the LW Sub organization.
- When a list of matching organizations displays, select the correct organization from the list.
Don't see the organization you wish to select as a Lien Waiver Only Sub-Tier?
The organization must be invited first. Use the Invite Organizations page to invite an off-system organization to use the system.
- In the Service field, enter a description of the service provided by the LW Sub.
- (Optional) Complete additional fields:
- Contract Number: The contract ID number for the LW Sub
- Notice Date: The date the Pre-Lien Notice was received
- Notice Amount: The amount of the Pre-Lien Notice.
- Optional. Add a preliminary notice.
- Select the Choose File button.
A File Upload dialog box displays.
- From the dialog box, select a file.
- Save the dialog box to return to the Add Sub-Tier page.
- Select the Choose File button.
- Select the Save button.
- A Status page confirms the lien waiver information has been saved.
- The Sub-Tier displays below the Prime Subcontractor on the Manage Lien Waivers page.