Applying Lien Waiver Holds
To apply lien waiver holds on the Manage Lien Waivers page:
- Select the correct draw from the Draw Selector near the top of the page.
Holds are placed on a per draw basis. You need to select a specific draw to apply holds to that period.
- Select the Apply Holds button.
- The approval status for all organizations with an orange GC Approval status changes to red.
- The Manage Lien Waivers, Manage Lien Waivers by Draw, and View Lien Waiver Status pages reflect the holds immediately.
Last Published Wednesday, July 10, 2024