Recording Progress Billing for Subcontractors

To enter progress billing details as a Subcontractor on the Progress tab of the your Billing Workflow:

  1. Navigate to Your Billing Workflow for Subcontractors
  2. Ensure that you are on the Progress tab.
    • The Progress tab will display first for most users beginning the invoicing process.
    • If a project allows stored material tracking, this will be the second tab in the invoicing process.
    • If the current draw does not allow progress billing, you will not see this tab.
  3. Enter billing amounts:
    1. Choose a line to bill against. The selected field will have a darker border than the other cells in the table.

      Unable to edit a field? Some General Contractors use component types to specify how labor or stored materials can be billed. Subcontractor billing is then limited by the component type.

    2. Enter an amount under the Work This Period column. 

      Once an amount billed is entered:

      • Amounts in the % CompleteCompleted to Date, and Net This Period are automatically calculated
      • The Retention Held This Period amount is automatically calculated.
        The retention calculation is based on the project's default percentage.
  4. Optional. Add comments to a line for later review or as a message to an on-system user. The line item comments entered here are visible to your General Contractor when they view or modify your invoice.
    1. In the Description of Work column, select the speech button icon.

      A Comments and History dialog box displays.

    2. In the available field in the dialog box, enter your comment.
    3. Select Ok.

      The dialog box closes and the speech bubble icon turns blue. Select the blue icon to view available comments.

  5. Optional. Use the Contract Level Changes option to quickly calculate billing for the final invoice on a project.
    1. From the More menu select the Contract Level Changes option.

      A dialog box displays.

    2. In the dialog box, select the Bill Full and Final check box.

      The application:

      • Automatically calculates all line items at 100% work completed
      • Reduces retention to 0%
      • Requests all previously held retention.

        Note: For the Bill Full and Final option to calculate work completed and retention requests, the current draw must allow progress and retention billing. If the draw does not allow both, the check box will not be active.

  6. Check the invoice totals at the bottom of the page.
  7. Select the Save & Continue button to progress to the next tab in your Billing Workflow.

There are two additional ways to update billing totals on the Progress tab:

  1. Bill for a completed percentage
  2. Bill for stored materials.

Bill % Complete

To bill based on percentage, update the amount in the % Complete fieldThe Work This Period field shows the dollar amount. All other fields are automatically calculated.

Tip

Invoice amounts may not exceed the remaining balance for any line item.

Bill for Material Stored This Period

Enter the dollar amount of material stored between the draw Period From and Period To dates in the Material Stored This Period field.

Notes: