Recording Stored Materials for General Contractors

To enter stored material amounts:

  1. Navigate to your Billing Workflow.
  2. Select the Stored Materials tab.
  3. Choose a line to bill against. If a line includes a subcontract, the Self-Performed and Contracted lines display beneath the Total line. You can enter amounts on the Total line or the Self-Performed line.
  4. On Site column fields:
    • Prior Stored Materials—Review this field to see the total amount of materials received on site before the current draw.
    • Consumed This Period—Use this field to record materials that are used during the current draw. Note: The materials may have been received in a prior period or in the current period. This field is not used to calculate payment.
    • Received This Period—Use this field to record materials that are received and stored on site during the current draw. Note: This field is used to calculate the payment.

      Note: The On Site Materials Stored to Date field includes the Prior Store Materials amount plus the Received This Period amount less the Consumed This Period amount.

  5. Off Site column fields:
    • Previous Store Materials—Review this field to see the total amount of materials received off site before the current draw.
    • Consumed This Period—Use this field to record materials that are used during the current draw.
    • Received This Period—Use this field to record materials that are received and stored off site during the current draw.

      Note: The Off Site Materials Stored to Date field includes the Prior Stored Materials amount plus the Received This Period amount less the Consumed This Period amount.

  6. Choose Save & Continue.

    Amounts added to the Stored Material tab are shown in the MaterialStored this Periodcolumns on the Progress tab.

Tips