Progress Tab Fields Overview
% Complete
Bill a percentage of work completed in the current draw and all previous draws. Entering an amount in this field will automatically adjust the Work This Period field.
Work This Period
Bill for the dollar amount of the work completed between the draw Period From and Period To dates. Entering an amount in this field will automatically adjust the % Completed field.
Material Stored This Period
Bill the for the dollar amount of material stored between the draw Period From and Period To dates. Entering an amount in this field will automatically adjust the Completed To Date % Complete fields.
Completed to Date
Bill for the total dollar amount of material stored for the current and previous draws. Entering an amount in this field will automatically adjust the Worked This Period field.
Balance
Amount left to bill on the contract (the total amount of work outstanding on the contract).
Retention % This Period
The percentage of your billing held as retention for the current draw. Entering an amount in this field will automatically adjust the Retention Held This Period field.
Retention Held This Period
The dollar amount of your billing held as retention for the current draw. Entering an amount in this field will automatically adjust the Retention % This Period field.
Net this Period
Displays the total amount billed for each line. (Work this Period + Materials Stored this Period - Retention Held This Period).
Scheduled Value
Current total value for the line item.
Self-Performed and Subcontractor Invoice Lines
Subcontractor invoices are rolled-up into the General Contractor's invoice.
Total line
The amount being billed to the Owner.
Self-Performed Line
A line the General Contractor can bill against, indicated by the General Contractor's name (the difference between the contracted and the total).
Contracted Line
A line that shows the Subcontractor's billing.
Attachments
Select the icon to add an attachment to the invoiced line. This column includes a count of how many attachments are currently uploaded for the line item.