Due Dates and Responses Report
Use the Due Dates and Responses Report to review and track deadline dates and activities for a selected draw to monitor compliance to the Ontario Construction Act requirements.
The following users can generate this report:
- All Enterprise Administrators
- All Local Administrators
- Regular Users assigned to a project.
Report Output
- Segment ID
- Project Number
- Project Name
- Subcontractor Name
- Subcontract Number
- Draw Number
- Draw Name
- GC's Invoice Number
- GC Invoice Date
- Owner Response Deadline Date
- Owner Response Date
- Sub Invoice Date
- Sub Response Deadline Date
- Sub Response Date
- Owner Funding Deadline Date
- Owner Funding Date
- Owner Funding Delay
- Subcontractor Payment Due Date
- Subcontractor Payment Date
- Subcontractor Payment Delay
- Owner Net Payment Due
- Owner Funding Amount
- Owner Unpaid Balance
- Subcontractor Net Payment Due
- Subcontractor Funded
- Subcontractor Unpaid Balance
Last Published Wednesday, July 10, 2024