To change the grace period for timesheet reporting:
- Click the Resource & Security Admin tab.
- Select the Manage Allowed Grace Period In Days For Activities in Timesheet Settings link.
- Choose an initiative and click the [Edit] link next to it. The Edit Allowed Grace Period In Days For Activities In Timesheet Settings screen is displayed.
- Specify how many days past the activity completion date can team members continue to report effort.
- Specify how many days before the activity start date can team members start reporting effort.
- Click Update.