Project (Cycle Time)

Component

Description

Drill Down

Drills To

 

Project Cycle Time by Period

  • Project Cycle Time by Period
  • The chart displays projects cycle time by various Phases on Y-Axis for projects that qualify the filter criteria and reporting period on X-Axis.
  • Projects that start in one year and end in the next year will be counted in both years.
  • Current quarter figures are as of the current date.
  • Current year is displayed as YYYYYTD e.g. 2009YTD.  YTD means Year to Date.
  • Prior quarter and year end figures are as of the last day of the period.
  • User can click on a bar to drill down to the list of projects that contribute to the bar.

Yes

Project Listing Report

 

Project Cycle Time by Role

  • Project Cycle Time by Role
  • The chart displays the average cycle time for projects on Y-Axis that qualify the filter criteria and Users on X-Axis.
  • User can click on a bar to drill down to the list of projects that contribute to the bar.
  • The user selection is based on the System Access Profile definition then must be further defined by an individual user level selection.

Yes

Project Listing Report

 

Project Cycle Time by Alignment

  • Project Cycle Time by Alignment
  • The chart displays the cycle time for projects that qualify the filter criteria on Y-Axis and immediate children of selected Alignment node on X-Axis.
  • This chart only works when the system has an Alignment (Strategy) configured.
  • Projects that are aligned to multiple alignments are counted in multiple alignments.
  • Click on a bar to drill down to the list of projects that contribute to the bar.
  • User can select to display by Average or Median days of the cycle time.

Yes

Project Listing Report

 

Project Cycle Time by Classification

  • Project Cycle Time by Classification
  • The chart displays the cycle time for projects that qualify the filter criteria on Y-Axis and the selected classification field on X-Axis.
  • Projects that are aligned to multiple classification fields will be counted in multiple classifications.
  • User can click on a bar to drill down to the list of projects that contribute to the bar.
  • In a multi-Initiative system, a selection must be made to specify the Initiative to be used.

Yes

Project Listing Report

 

Project Cycle Time by Phase

  • Project Cycle Time by Phase (Box Chart)
  • The chart displays box plot of cycle tie on Y-Axis and Phases X-Axis.
  • If one Roadmap is selected in the filter, then the Phases are displayed the order specified in the Roadmap.
  • If multiple Roadmaps are selected in the filter, then the Phases are displayed alphabetically.
  • Only the completed phases will be counted towards calculation of the box plot as on-going (or active) phase does not have the actual end date of the phase.

Yes

Project Listing Report

 

Project Cycle Time by Organization

  • Project Cycle Time by Organization
  • The chart displays the cycle time for projects on Y-Axis that qualify the filter criteria and Organization on X-Axis.
  • User can select different level of organization to show on the X-Axis from the filter criteria.
  • Projects that aligned to multiple organizations will be counted in multiple organizations.
  • User can click on a bard to drill down to the list of projects that contribute to the bar.

Yes

 

Project Listing Report

 

Project Cycle Time by Custom Fields

  • Project Cycle Time by Custom Fields
    The chart displays the cycle time for projects that qualify the filter criteria on the Y-axis, and the selected custom field on the X-axis. The custom fields are set by your Administrator and can be modified by clicking the Edit Filters button.
  • Click on a bar to drill down to the list of projects.

Yes

Project Listing Report

See Also

Available Dashboard Components

Proposals (Charters)

Projects (General)

Projects (Count)

Projects (Finances)

Projects (Metrics)

Resource



Legal Notices | Your Privacy Rights
Copyright © 2000, 2020

Last Published Tuesday, June 9, 2020