To enter metric tracking data:
- Navigate to the Metrics page by selecting Project Module Menu (Project #) > Go To > Metrics, or clicking the Metrics link on the left navigation bar within a particular project.
- Locate the metric for which you wish to add data and click the [Data] link in the Action column.
- Select the date for which you are about to enter data.
- Enter the data in the appropriate fields.
Note: The system will automatically advance the date to the next logical date for data entry based on the tracking frequency, for example, If the tracking frequency is 1 week and you enter data for Sept 1, the date is automatically advanced to Sept 8.
- Click the Add button. The data will be displayed on the same page. You may edit or delete any metric data points as needed.
- Click Chart to view the data as a graph.
- Click Done to save your changes.