Synchronizing Business Events

Business Event Synchronization enables you to capture past business event data and upload it to external systems. You should ensure that all users are logged out before running this utility. The synchronization process may cause a slowdown of the application.

To activate Business Event Synchronization:

  1. From the OPERA Toolbox menu, select Utilities.
  2. Select Synchronization and then select Business Events.
  3. Select a property as the source of business events data.
  4. Select the external system as the destination of your upload.
  5. Select the check box belonging to the modules you wish to synchronize.
  6. For each module you select, make any additional selections to refine the data upload.
    For example, select date ranges for the requested data. Or, if selecting the Blocks module, specify either the Begin dates or the Stay dates.
  7. Click Synchronize Business Events.