Installation Option: Easy 1st Install

For use with Oracle Talari D2000 as a Router (Gateway, Fail to Block), Layer 2 Fail to Wire (Overlay), MPLS & Internet Hybrid.

Easy 1st Install Site Deployment Criteria

NCN:

  • Easy 1st Install can be used once the Network Control Node (NCN) has been set up for your network.
  • Active Appliance Package: The NCN must be running an active configuration which includes the Oracle Talari D2000 for the site being installed.

Client Side Connectivity:

  • Internet, DHCP, and DNS connectivity to the management interface are required to use Easy 1st Install. If one or more are not available, please see the instructions for manual installation. If the management interface is connected to the LAN segment, communication with the public Internet will be blocked and Easy 1st Install will fail.
  • Cable the LAN and WAN ports in accordance with the Talari configuration for the site.

Use NCN to Upload Client Package to Registration Server

  1. Log in to the Web Console of the NCN.
  2. Navigate to Configuration > Easy Install.
  3. Locate the Site name of the Oracle Talari D2000 being deployed.
  4. Click the Edit pencil to open the Set Serial Number window.
  5. Enter the serial number of the Oracle Talari D2000 being deployed and click the Set Serial Number button.

    The serial number may be found on the top of the Oracle Talari D2000 above the left-hand drive bays.

  6. Observe the Upload/Activate column. Click the Upload/Activate text when it appears.
  7. Continue to observe the Upload/Activate column. Once the text reads Upload Complete, proceed to the next section.

Deploy the Talari Appliance

  1. Cable the Oracle Talari D2000 with the provided cables.
  2. Ensure that the appliance management interface is cabled for Internet connectivity.
  3. Connect the power cords to the Oracle Talari D2000. Connect the other ends to an appropriately grounded power source. The Oracle Talari D2000 will power on automatically.
  4. The Oracle Talari D2000 will begin the Easy 1st Install process. Please allow up to ten minutes for the process to complete. (From the NCN Web Console, observe the Configuration > Easy Install page for status updates during installation.)
  5. Once the Easy 1st Install process has completed, the Talari service will automatically be enabled.
  6. To access the Management IP address of the Oracle Talari D2000 via the conduit after deployment is complete, move the blue management cable to the LAN switch.