# |
P6 field name in dropdown |
P6 field name in Power Client |
Data Type |
---|---|---|---|
1 |
AddActualToRemaining |
Add Actual To Remain |
Flag |
2 |
AddedBy |
Added By |
Text |
3 |
AnnualDiscountRate |
|
|
4 |
AnticipatedFinishDate |
Anticipated Finish |
Date |
5 |
AnticipatedStartDate |
Anticipated Start |
Date |
6 |
CheckOutDate |
Date Checked Out |
Date |
7 |
ContainsSummaryData |
Contains Summary Data |
Flag |
8 |
ContainsSummaryDataOnly |
Contains Summarized Data Only |
Flag |
9 |
CreateDate |
|
|
10 |
CreateUser |
|
|
11 |
CurrentBudget |
Current Budget |
Cost |
12 |
CurrentVariance |
Current Variance |
Cost |
13 |
DataDate |
Data Date |
Date |
14 |
DateAdded |
Date Added |
Date |
15 |
DiscountApplicationPeriod |
|
|
16 |
DistributedCurrentBudget |
Distributed Current Budget |
Cost |
17 |
EarnedValueETCUserValue |
|
|
18 |
EarnedValueUserPercent |
|
|
19 |
EstimatedWeight |
|
|
20 |
FinishDate |
Finish |
Date |
21 |
FiscalYearStartMonth |
|
|
22 |
ForecastFinishDate |
Forecast Finish Date |
Date |
23 |
ForecastStartDate |
Forecast Start Date |
Date |
24 |
HasFutureBucketData |
|
|
25 |
IndependentETCLaborUnits |
Independent ETC Labor Units |
Integer |
26 |
IndependentETCTotalCost |
Independent ETC Total Cost |
Cost |
27 |
LastSummarizedDate |
Last Summarized Date |
Date |
28 |
LastUpdateDate |
|
|
29 |
LastUpdateUser |
|
|
30 |
LevelingPriority |
Project Leveling Priority |
Integer |
31 |
MustFinishByDate |
Must Finish By |
Date |
32 |
Name |
Project Name |
Text |
33 |
OBSName |
Resposinble Manager |
Text |
34 |
OriginalBudget |
Original Budget |
Cost |
35 |
OverallProjectScore |
|
|
36 |
PlannedStartDate |
Planned Start |
Date |
37 |
ProjectForecastStartDate |
Project Forecast Start |
Date |
38 |
ProposedBudget |
Proposed Budget |
Cost |
39 |
RiskLevel |
Risk Level |
ValueList |
40 |
ScheduledFinishDate |
|
|
41 |
StartDate |
Start |
Date |
42 |
Status |
Project Status |
ValueList |
43 |
StrategicPriority |
Strategic Priority |
Special |
44 |
SummaryAccountingVarianceByCost |
Accounting Variance |
Cost |
45 |
SummaryAccountingVarianceByLaborUnits |
Accounting Variance - Labor Units |
Integer |
46 |
SummaryActivityCount |
Total Activities |
ActivitesRelated |
47 |
SummaryActualDuration |
Actual Duration |
Integer |
48 |
SummaryActualExpenseCost |
Actual Expense Cost |
Cost |
49 |
SummaryActualFinishDate |
Actual Finish |
Date |
50 |
SummaryActualLaborCost |
Actual Labor Cost |
Cost |
51 |
SummaryActualLaborUnits |
Actual Labor Units |
Integer |
52 |
SummaryActualMaterialCost |
Actual Material Cost |
Cost |
53 |
SummaryActualNonLaborCost |
Actual Nonlabor Cost |
Cost |
54 |
SummaryActualNonLaborUnits |
Actual Nonlabor Units |
Integer |
55 |
SummaryActualStartDate |
Actual Start |
Date |
56 |
SummaryActualThisPeriodCost |
|
|
57 |
SummaryActualThisPeriodLaborCost |
Actual This Period Labor Cost |
Cost |
58 |
SummaryActualThisPeriodLaborUnits |
Actual This Period Labor Units |
Integer |
59 |
SummaryActualThisPeriodMaterialCost |
Actual This Period Material Cost |
Cost |
60 |
SummaryActualThisPeriodNonLaborCost |
Actual This Period Nonlabor Cost |
Cost |
61 |
SummaryActualThisPeriodNonLaborUnits |
Actual This Period Nonlabor Units |
Integer |
62 |
SummaryActualTotalCost |
Actual Total Cost |
Cost |
63 |
SummaryActualValueByCost |
|
|
64 |
SummaryActualValueByLaborUnits |
|
|
65 |
SummaryAtCompletionDuration |
At Completion Duration |
Integer |
66 |
SummaryAtCompletionExpenseCost |
At Completion Expense Cost |
Cost |
67 |
SummaryAtCompletionLaborCost |
At Completion Labor Cost |
Cost |
68 |
SummaryAtCompletionLaborUnits |
At Completion Labor Units |
Integer |
69 |
SummaryAtCompletionMaterialCost |
At Completion Material Cost |
Cost |
70 |
SummaryAtCompletionNonLaborCost |
At Completion Nonlabor Cost |
Cost |
71 |
SummaryAtCompletionNonLaborUnits |
At Completion Nonlabor Units |
Integer |
72 |
SummaryAtCompletionTotalCost |
At Completion Total Cost |
Cost |
73 |
SummaryAtCompletionTotalCostVariance |
|
|
74 |
SummaryBaselineCompletedActivityCount |
BL Project Completed Activities |
ActivitesRelated |
75 |
SummaryBaselineDuration |
BL Project Duration |
Integer |
76 |
SummaryBaselineExpenseCost |
BL Project Expense Cost |
Cost |
77 |
SummaryBaselineFinishDate |
BL Project Finish |
Date |
78 |
SummaryBaselineInProgressActivityCount |
BL Project In-Progress Activities |
ActivitesRelated |
79 |
SummaryBaselineLaborCost |
BL Project Labor Cost |
Cost |
80 |
SummaryBaselineLaborUnits |
BL Project Labor Units |
Integer |
81 |
SummaryBaselineMaterialCost |
BL Project Material Cost |
Cost |
82 |
SummaryBaselineNonLaborCost |
BL Project Nonlabor Cost |
Cost |
83 |
SummaryBaselineNonLaborUnits |
BL Project Nonlabor Units |
Integer |
84 |
SummaryBaselineNotStartedActivityCount |
BL Project Not-Started Activities |
ActivitesRelated |
85 |
SummaryBaselineStartDate |
BL Project Start |
Date |
86 |
SummaryBaselineTotalCost |
BL Project Total Cost |
Cost |
87 |
SummaryBudgetAtCompletionByCost |
Budget At Completion |
Cost |
88 |
SummaryBudgetAtCompletionByLaborUnits |
Budget At Completion (BAC) - Labor Units |
Integer |
89 |
SummaryCompletedActivityCount |
Actual Completed Activities |
ActivitesRelated |
90 |
SummaryCostPercentComplete |
Cost % Complete |
PercentComplete |
91 |
SummaryCostPercentOfPlanned |
Cost % Of Planned |
PercentComplete |
92 |
SummaryCostPerformanceIndexByCost |
Cost Performance Index |
Unkown |
93 |
SummaryCostPerformanceIndexByLaborUnits |
Cost Performance Index - Labor Units |
Unkown |
94 |
SummaryCostVarianceByCost |
Cost Variance |
Cost |
95 |
SummaryCostVarianceByLaborUnits |
Cost Variance - Labor Units |
Integer |
96 |
SummaryCostVarianceIndex |
|
|
97 |
SummaryCostVarianceIndexByCost |
Cost Variance Index |
Unkown |
98 |
SummaryCostVarianceIndexByLaborUnits |
Cost Variance Index - Labor Units |
Unkown |
99 |
SummaryDurationPercentComplete |
|
|
100 |
SummaryDurationPercentOfPlanned |
Duration % Of Planned |
PercentComplete |
101 |
SummaryDurationVariance |
|
|
102 |
SummaryEarnedValueByCost |
Earned Value Cost |
Cost |
103 |
SummaryEarnedValueByLaborUnits |
Earned Value - Labor Units |
Integer |
104 |
SummaryEstimateAtCompletionByCost |
Estimate At Completion Cost |
Cost |
105 |
SummaryEstimateAtCompletionByLaborUnits |
Estimate At Completion - Labor Units |
Integer |
106 |
SummaryEstimateAtCompletionHighPercentByLaborUnits |
|
|
107 |
SummaryEstimateAtCompletionLowPercentByLaborUnits |
|
|
108 |
SummaryEstimateToCompleteByCost |
Estimate To Complete |
Cost |
109 |
SummaryEstimateToCompleteByLaborUnits |
Estimate To Complete - Labor Units |
Integer |
110 |
SummaryExpenseCostPercentComplete |
Expense Cost % Complete |
PercentComplete |
111 |
SummaryExpenseCostVariance |
Variance - BL Project Expense Cost |
Cost |
112 |
SummaryFinishDateVariance |
|
|
113 |
SummaryInProgressActivityCount |
Actual In-Progress Activities |
ActivitesRelated |
114 |
SummaryLaborCostPercentComplete |
Labor Cost % Complete |
PercentComplete |
115 |
SummaryLaborCostVariance |
Variance - BL Project Labor Cost |
Cost |
116 |
SummaryLaborUnitsPercentComplete |
Labor Units % Complete |
PercentComplete |
117 |
SummaryLaborUnitsVariance |
Variance - BL Project Labor Units |
Integer |
118 |
SummaryMaterialCostPercentComplete |
Material Cost % Complete |
PercentComplete |
119 |
SummaryMaterialCostVariance |
Variance - BL Project Material Cost |
Cost |
120 |
SummaryNonLaborCostPercentComplete |
Nonlabor Cost % Complete |
PercentComplete |
121 |
SummaryNonLaborCostVariance |
Variance - BL Project Nonlabor Cost |
Cost |
122 |
SummaryNonLaborUnitsPercentComplete |
Nonlabor Units % Complete |
PercentComplete |
123 |
SummaryNonLaborUnitsVariance |
Variance - BL Project Nonlabor Units |
Integer |
124 |
SummaryNotStartedActivityCount |
Actual Not-Started Activities |
ActivitesRelated |
125 |
SummaryPerformancePercentCompleteByCost |
|
|
126 |
SummaryPerformancePercentCompleteByLaborUnits |
|
|
127 |
SummaryPlannedValueByCost |
|
|
128 |
SummaryPlannedValueByLaborUnits |
|
|
129 |
SummaryProgressFinishDate |
|
|
130 |
SummaryRemainingDuration |
Remaining Duration |
Integer |
131 |
SummaryRemainingExpenseCost |
Remaining Expense Cost |
Cost |
132 |
SummaryRemainingFinishDate |
|
|
133 |
SummaryRemainingLaborCost |
Remaining Labor Cost |
Cost |
134 |
SummaryRemainingLaborUnits |
Remaining Labor Units |
Integer |
135 |
SummaryRemainingMaterialCost |
Remaining Material Cost |
Cost |
136 |
SummaryRemainingNonLaborCost |
Remaining Nonlabor Cost |
Cost |
137 |
SummaryRemainingNonLaborUnits |
Remaining Nonlabor Units |
Integer |
138 |
SummaryRemainingStartDate |
|
|
139 |
SummaryRemainingTotalCost |
Remaining Total Cost |
Cost |
140 |
SummarySchedulePercentComplete |
|
|
141 |
SummarySchedulePercentCompleteByLaborUnits |
|
|
142 |
SummarySchedulePerformanceIndexByCost |
|
|
143 |
SummarySchedulePerformanceIndexByLaborUnits |
|
|
144 |
SummaryScheduleVarianceByCost |
Schedule Variance |
Cost |
145 |
SummaryScheduleVarianceByLaborUnits |
Schedule Variance - Labor Units |
Integer |
146 |
SummaryScheduleVarianceIndex |
|
|
147 |
SummaryScheduleVarianceIndexByCost |
|
|
148 |
SummaryScheduleVarianceIndexByLaborUnits |
|
|
149 |
SummaryStartDateVariance |
|
|
150 |
SummaryToCompletePerformanceIndexByCost |
To Complete Performance Index |
Unkown |
151 |
SummaryTotalCostVariance |
|
|
152 |
SummaryTotalFloat |
|
|
153 |
SummaryUnitsPercentComplete |
|
|
154 |
SummaryVarianceAtCompletionByLaborUnits |
Variance At Completion - Labor Units |
Integer |
155 |
TotalBenefitPlan |
Total Benefit Plan |
Cost |
156 |
TotalBenefitPlanTally |
Total Benefit Plan Tally |
Cost |
157 |
TotalFunding |
Total Funding |
Cost |
158 |
TotalSpendingPlan |
Total Spending Plan |
Cost |
159 |
TotalSpendingPlanTally |
Total Spending Plan Tally |
Cost |
160 |
UnallocatedBudget |
Unallocated Budget |
Cost |
161 |
UndistributedCurrentVariance |
Undistributed Current Variance |
Cost |
162 |
WebSiteRootDirectory |
Web Site Root Directory |
Text |
163 |
WebSiteURL |
Project Web Site URL |
Text |