Add one or more response plans to a risk to plan alternative activities that might reduce the probability of a risk occurring, or to reduce the impact of the risk.
- Click Projects.
 - On the Projects navigation bar, click Risks.
 - On the Risks page, click a risk, and then click the Response Plans detail window.
 - On the Response Plans detail window:
- Click Add
 and select Response Plan. - In the ID field, double-click and type a response plan ID.
 - In the Name field, double-click and type a name for the new response plan.
 - In the Response Type field, double-click and select a response type from the list.
 
 - Click Add
 - On the Risks page, click Save.
Note: After you decide which response plan you are implementing, select the Active option next to the appropriate response plan.