Specifying Resource Assignment Rates

You can set rate information for resources or roles.

To specify resource assignment rates:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page, select an activity in the table and click the Assignments detail window.
  4. In the Assignments detail window:
    1. Add the Rate Type and Rate Source columns.
    2. Select an option for the type and source.
    3. Save your changes.

Tips

When you save your changes, costs for the assignment are recalculated based on the new rate: Cost equals Units times Price/Unit. You can add the Price/Unit column to the detail window to view the price used. To manually specify a price/unit, select Override in the Rate Source field and type a value in the Price/Unit field.

Related Topics

About Resource Assignments

Assigning Resources to an Activity

Configuring Activity Resources

Adding Activity Resource Estimates

Showing or Hiding Columns in a Table