Risks Page

Overview

Use this page to add, modify, or delete project risks.

Note: If the Probability, Schedule, and Cost fields are disabled, a risk scoring matrix is not assigned to the current project. You can still enter risk data on this page; however, a risk scoring matrix must be assigned to a project to perform qualitative risk analysis.

Screen Elements

Add button

Adds an item to the table.

Expand All

Enables you to see all of the items in a hierarchical list.

Collapse All

Enables you to hide subordinate items in a hierarchical list.

Full Screen

Expands the current work area so it fills the entire display.

Print

Prints the Grid View.

Customize View

Opens the Customize View dialog box.

Search

Enables you to perform a search based on the value you enter in the search bar.

Risk Table

ID field

The unique identifier for the risk.

Name field

The name for a particular type of risk classification.

Type list

Determines whether a risk is a threat or an opportunity.

A threat will have a negative impact on your project, while an opportunity can have a perceived benefit to the project.

Status field

The current state of the risk.

Proposed: The risk is identified and awaits approval.

Open: The risk is approved as a valid risk to the project.

Active: The risk is currently impacting the project.

Rejected (Closed): The risk is not seen as a valid risk to the project and therefore will not be tracked and managed by the project. The data for this risk cannot be modified once it is closed.

Managed (Closed): The risk occurred and was successfully managed by the project team and is no longer an active risk. The data for this risk cannot be modified once it is closed.

Impacted (Closed): The risk occurred, impacted the project and is no longer an active risk. The data for this risk cannot be modified once it is closed.

Owner field

The resource who has ownership of the risk.

Probability field

The probability of the risk occurring.

Schedule field

The impact on the schedule if the risk occurs.

Cost field

The monetary impact on the project if the risk occurs.

Score field

The risk calculation based on the values defined for probability, cost impact, schedule impact, and any additional user-defined impacts for the risk.

Response Total Cost field

The total cost of the active response plan.

If a response plan is active, this field is disabled and displays the sum of the Remaining Cost plus Actual Cost fields for all response action items in the response plan. Rejected response action items are not included in the calculation.

risk table

Download

Enables you to download the view as an Excel file. For hierarchical data, the top level and any expanded levels are downloaded. For flat lists, all columns are downloaded.

Collapse Dock

Collapses the dock.

Show/Hide Tabs

Enables you to configure which tabs are shown and hidden.

Previous Record button

Shows the previous record.

Previous Record button

Advances to the next record.

Risks Page detail windows:

Response Plans Detail Window of the Risks Page

Activities Detail Window of the Risks Page

Risk Details Window of the Risks Page

Probability and Impact Diagram Detail Window of the Risks Page

UDF Detail Window of the Risks Page

Getting Here

  1. Click Projects.
  2. On the Projects navigation bar, click Risks.

Related Topics

About Risks

Working with Project Risks

Managing Project Risks